top of page
Writer's pictureAdmin

Lagos-Ibadan rail: Amaechi gives update, confirms 90 percent completion

Rotimi Amaechi, Minister of Transport, has said construction work at the ongoing Lagos-Ibadan Standard Gauge has reached about 90 per cent completion.

Amaechi disclosed this while inspecting the project at Ewekoro-Papalanto axis of the project on Monday.

“We are progressing but there is no way they can fast-track the project during the raining season, but 90 per cent of the construction works has been done”, NAN quoted him as saying.

“I have told them to work day and night, to ensure the project keeps moving as expected, especially on the bridges and construction of modern station at Ebuta-Meta Lagos.

“I also told them that two weeks after the rain mush have stopped, they have to complete the remaining 10 per cent to allow them focus on laying of tracks”.

According to him, by the end of October they, should have finished all the bridges from Iju to Abeokuta.

The minister said that laying of tracks would be an easy task after all the earthworks must have been completed.

Amaechi called on the contractor – China Civil Engineering Construction Company (CCECC) – to expedite action on the pace of work to ensure timely delivery of the project.

The minister said that the major challenge facing the project now was where to site the railway stations at various towns and communities along the corridor.

“Where to locate the railway stations has posed a great challenge as many communities find it difficult to release their land for such.

“We have such challenges in Abeokuta, Agege and other vital areas, where we needed to site the stations.

“It won’t be ideal after finishing the construction work and there is no rail station for people to board their train, but we are talking to the communities.

“Let them know the benefit of the stations to their communities,” he said.

According to him, the challenges of pipelines and cables in Lagos state have been resolved by casing the underground pipes for more protections against the vibrations of the train.

He said that shifting the pipelines from the present locations to other places would cost more and prolong the project more than the slated delivery time.

Amaechi said that efforts had been put in place by the contractor to safeguard the pipelines by fixing casing on it to ensure proper protection from the rail vibrations.

0 views0 comments

Comments


bottom of page